SAP PS Functional Consultant Interview: Most Asked Questions and Answers

Younas

Updated: Mar 17



SAP PS Interview Questions



1. What is SAP Project System (PS) ?


SAP Project System (PS) is a comprehensive module in SAP designed to support the planning, execution, and monitoring of projects across various industries. It provides tools and functionalities to manage project structures, resources, costs, and timelines effectively. SAP PS ensures seamless integration with other SAP modules like MM (Material Management), SD (Sales and Distribution), FI (Financial Accounting), CO (Controlling), and PP (Production Planning) to enable end-to-end project management.


Key functionalities of SAP PS include:


  • Project Structuring: Define and manage project structures using Work Breakdown Structures (WBS) and Networks.

  • Planning: Facilitate cost, resource, and schedule planning to ensure project objectives are met efficiently.

  • Budgeting: Establish and monitor project budgets to control expenditures.

  • Scheduling: Plan and control project timelines using network activities and milestones.

  • Resource Management: Allocate internal and external resources effectively.

  • Progress Tracking: Monitor project status and track the completion of activities and milestones.

  • Cost Tracking and Controlling: Capture, monitor, and control project costs throughout the lifecycle.

  • Billing: Manage customer billing processes through milestone or resource-related billing.

  • Reporting: Generate comprehensive reports for project analysis and decision-making.

  • Integration: Ensure smooth data flow and process integration with other SAP modules for consistent project management.


2. What are the key components of SAP PS ?


  • Work Breakdown Structure (WBS): A hierarchical structure that defines the project scope.

  • Network: Represents the sequence of activities and their dependencies.

  • Activities: Tasks that need to be performed within a project.

  • Milestones: Key checkpoints within a project for monitoring progress.

  • Project Definition: The overall framework and essential parameters of a project.


3. What is the difference between WBS and Network ?


  • WBS is used for structuring and organizing the project in a hierarchical manner.

  • Network is used for scheduling and planning the detailed execution steps, showing the relationship between different activities.


4. How does integration work in SAP PS ?


SAP PS integrates with various modules like:


  • MM (Material Management): For material procurement.

  • SD (Sales and Distribution): For managing project-related sales processes.

  • FI (Financial Accounting): For tracking project-related costs and revenues.

  • CO (Controlling): For cost control and internal reporting.

  • PP (Production Planning): For managing production orders linked to projects.


5. How are costs planned and controlled in SAP PS ?


Costs are planned using cost planning methods such as:


  • Manual Planning: Entering costs directly against WBS elements.

  • Automatic Planning: Done through network activities where costs are calculated based on activity rates, material assignments, cost activities, and other project-related components. This method ensures dynamic cost estimation based on project activities.


6. How is budgeting and availability control handled in SAP PS ?


  • Budgeting: This involves assigning a budget to WBS elements to ensure proper cost tracking. It is essential for monitoring financial performance and ensuring that project costs stay within approved limits.

  • Availability Control: This mechanism ensures that expenditures and commitments do not exceed the allocated budget. SAP triggers warnings or errors if the budget is about to be exceeded, helping maintain financial discipline.


7. What are the types of activities in SAP PS ?


  • Internal Activities: Performed by internal resources and require work centers.

  • External Activities: Outsourced to vendors.

  • Service Activities: Activities related to procuring services.

  • Cost Activities: Used for planning and monitoring costs.


8. What is a milestone and how is it used in SAP PS ?


Milestones are significant events within a project that are used for:


  • Progress tracking to monitor the project's advancement.

  • Triggering milestone billing for payment processes.

  • Releasing subsequent project phases upon completion of prior stages.


9. How is billing handled in SAP PS ?


Billing in SAP PS can be managed using two primary methods:


  • Milestone Billing: Billing is triggered when specific project milestones are achieved. This method ensures payment is aligned with the completion of key project phases.

  • Resource-Related Billing: This method is based on actual resources consumed, such as time, materials, and services. Billing is generated based on the confirmed activities and actual usage, ensuring accurate cost recovery.


10. How is resource planning handled in SAP PS ?


Resources are planned using:


  • Work Centers: To allocate internal resources.

  • Resource Planning Profiles: For assigning required resources to activities.

  • Capacity Planning: To ensure resources are not over or under-utilized.


11. What is a Network Activity ?


A network activity defines the tasks, their sequence, duration, and resources. It forms the basis of scheduling and cost planning in SAP PS.


12. What is the purpose of assigning relationships in SAP PS networks ?


Assigning relationships in SAP PS networks defines the sequence and dependency between activities. These relationships, such as finish-to-start or start-to-start, help in scheduling and determining the order in which activities must be executed. Proper assignment ensures accurate project timelines, efficient resource utilization, and critical path analysis.


13. What is the role of CN41N in SAP PS ?


CN41N is a transaction code used for displaying project structures and generating project reports.


14. How is progress tracking done in SAP PS ?


  • Using Milestones to monitor key events.

  • Confirmation of Activities to record progress.

  • Progress Analysis reports for comparing planned vs. actual progress.


15. What is the process for period-end closing in SAP PS ?


  • Ensure all transactions are posted.

  • Perform cost settlements.

  • Run progress and status reports.

  • Close the periods in relevant modules.


16. What are User Status and System Status in SAP PS ?


  • System Status: Automatically managed by the system (e.g., Created, Released).

  • User Status: Custom-defined statuses for additional control and monitoring.


17. How do you handle project settlements ?


  • Assign settlement rules to WBS elements and networks.

  • Execute settlement transactions to transfer costs to the final cost object (e.g., asset, cost center).


18. What are the key reports used in SAP PS ?


  • CN41N: Project structure report.

  • S_ALR_87013542: Cost report for WBS elements.

  • S_ALR_87013558: Availability control report.

  • CJI3/CJI3N: Actual line item reports that provide detailed cost and revenue information for projects, enabling detailed analysis of financial data.


19. What is a Project Profile in SAP PS ?


A Project Profile defines default settings for projects like controlling area, company code, network and cost profiles, ensuring consistency in project creation.


20. What is the purpose of project versions in SAP PS ?


Project versions in SAP PS are used to store snapshots of project data at specific points in time. This allows comparison between planned, actual, and forecasted data for better monitoring and decision-making.


21. How is capacity overload managed in SAP PS ?


Capacity overload is managed by leveling activities, rescheduling tasks, or adjusting resource allocations to ensure that resource utilization stays within available capacity limits.


22. What are the types of costs in SAP PS ?


  • Primary Costs: Costs directly related to the consumption of goods or services.

  • Secondary Costs: Internal costs like overheads allocated through internal processes.


23. What is the role of project milestones in controlling project timelines and deliverables ?


Project milestones are key checkpoints that ensure specific deliverables are achieved at predefined stages. They help in controlling project timelines, trigger subsequent phases, and facilitate progress evaluations and billing processes.


24. How is cross-application time sheet (CATS) integrated with SAP PS ?


CATS (Cross-Application Time Sheet) is a central tool in SAP that enables employees to record their working hours for various tasks and projects. Its integration with SAP Project System (PS) ensures efficient and accurate time management, cost tracking, and resource allocation.


Here's how the integration works:

a. Time Recording: Employees can enter their working hours in CATS, specifying details such as the WBS (Work Breakdown Structure) elements, network activities, and cost centers related to a particular project.


b. Data Validation: CATS ensures that the entered data is validated against the project structures and network activities in SAP PS. This helps prevent incorrect postings and ensures data accuracy.


c. Approval Process: Recorded times can be subjected to an approval workflow, ensuring that project managers or supervisors validate and approve time entries before they impact cost accounting.


d. Transfer to SAP PS: Once approved, the recorded times are transferred to SAP PS, where they are posted against the relevant WBS elements or network activities. This integration ensures real-time tracking of project progress and associated costs.


e. Cost Allocation: The posted working times contribute to the calculation of actual costs in SAP PS. This allows for accurate cost allocation, budget monitoring, and variance analysis.


f. Resource Management: The integration helps in effective resource management by providing insights into resource utilization and availability, ensuring that projects stay on track.


g. Reporting and Analysis: With CATS integrated into SAP PS, organizations can generate comprehensive reports to analyze time consumption, project costs, and performance metrics, aiding in better decision-making.

This seamless integration ensures that project managers have accurate and timely data, helping in efficient project execution and financial control.


25. What are the challenges faced by SAP PS Consultants ?


  • Managing complex project structures.

  • Ensuring accurate integration with other modules.

  • Ensuring accurate cost tracking and control.

  • Handling change requests efficiently.


This comprehensive Q&A guide will help you prepare for your SAP PS functional consultant interview by covering the most relevant and frequently asked questions.


If you have any more questions or insights, feel free to add them in the comments section!

 
 
 